Construction Updates
Stay Updated
A free text-in service is being used to communicate any major traffic changes. To subscribe, simply text “US385” to 605-566-4041. Subscribers can unsubscribe at any time.
For regular updates on project progress, detour information, and more, sign up for our newsletter:
Construction Zone Reminders
- Follow posted speed limits in construction zones.
- Be aware of flaggers and other construction workers in the construction area.
- If you are following a pilot car, stay with the line, and do not stop or exit your vehicle in the project area.
Milling Work to Begin
On Monday, April 7, 2025, the contractor will begin milling (removing the existing pavement) on U.S. Highway 385 from one-half mile south of Sheridan Lake Road to Calumet Road and from the south end of Pactola Dam to just north of McCurdy Gulch Road. Motorists can expect flaggers and pilot cars throughout the Phase 2 construction area, large machinery, narrowed driving lanes, increased noise and dust, and a loose gravel surface. Please drive with caution. To avoid travel delays and driving on rough surfaces, drivers are recommended to consider using an alternate route. The recommended alternative route is S.D. Highway 44 and U.S. Highway 16.
Current Construction
- Phase 2 construction operations currently involve off-road grading, tree clearing, and logging operations. The contractor is using a pilot car and flaggers as needed from 7 a.m. to 6 p.m. (MT) on weekdays and some Saturdays.
- Blasting with traffic impacts is scheduled to take place beginning Tuesday, March 25, 2025, through Sunday, April 27, 2025. For more information, review the update from Monday, March 17, 2025. Users of Highway 385 can expect temporary road closures causing up to one hour of delay during rock blasting and subsequent rockfall cleanup. The public is advised to stay away from the drilling and blasting area during this time. To avoid unknown wait times, please consider using an alternative route.
Upcoming Construction
- Phase 1 (Pactola Dam to the Pennington-Lawrence County Line) permanent surfacing takes place this summer and will be completed by the end of July 2025. Currently, there are approximately two miles of gravel and three miles of hard surface between Pactola Dam and the Pennington-Lawrence County Line. During this time period, roadway users can expect the use of flaggers and pilot cars with delays up to15 minutes.
- Closure C (Sheridan Lake Road to Be Still Road) takes effect on Monday, April 28, 2025, and ends Friday, June 13, 2025. During this time period, the closed roadway will not be open to through traffic. Outside of the closure, but within the construction area, travelers can expect pilot cars and wait times, the use of large construction equipment, narrowed driving lanes, and loose gravel surfacing.
- Closure D (Be Still Road to Calumet Road) begins on Tuesday, Aug. 12, 2025, and ends on Friday, Oct. 17, 2025. Closure E (Pactola Dam to Taylor Ranch Road) begins on Monday, Oct. 20, 2025, and ends on Friday, March 6, 2026.
February Drone Flyover


Controlled Rock Blasting Scheduled for Tuesday, March 25, 2025, and Thursday, March 27, 2025: Expect One Hour Delay
March 25, 2025 – April 27, 2025
Beginning Tuesday, March 25, 2025, the contractor will be conducting planned rock blasting to remove rock material. During these controlled detonations, a portion of U.S. Highway 385 will be closed to through traffic for up to one hour. The following controlled rock blasts are scheduled to take place in March. Additional road closures as a result of controlled rock blasts will take place in April and will be shared at least 48 hours in advance via the project website, press release, and text message.
Scheduled Closures:
Tuesday, March 25, 2025, and Thursday, March 27, 2025
Between 10 a.m. and 2 p.m.
Closure in place from Sheridan Lake Road to Horse Creek Road.
Anticipated Closures:
The contractor is anticipating additional temporary closures of Highway 385 for up to one hour at a time for controlled rock blasting in the area between Sheridan Lake Road and Horse Creek Road in March and April. Exact dates and times are unknown but will be shared at least 48 hours in advance.
Up to two temporary road closures are expected to take place between Calumet Road and Sheridan Lake Road in April. Exact dates and times are unknown but will be shared at least 48 hours in advance.
How to Stay Up to Date:
A free text-in service is being used to communicate temporary road closures due to rock blasting, when the road opens, and any additional delays. To subscribe, simply text “US385” to 605-566-4041. Subscribers can unsubscribe at any time.

Click on image to enlarge.
Current Construction
- Phase 2 construction operations currently involve off-road grading, tree clearing, and logging operations.
- The contractor is using a pilot car and flaggers as needed from 7 a.m. to 6 p.m. (MT) on weekdays and some Saturdays.
- Rock blasting is anticipated to take place on U.S. Highway 385 one-half mile north of Sheridan Lake Road during the week of March 17, 2025.
- Blasting times are yet to be determined. Users of Highway 385 can expect temporary road closures causing up to one hour of delay during rock blasting and subsequent rockfall cleanup.
- The public is advised to stay away from the drilling and blasting area during this time. To avoid unknown wait times, please consider using an alternative route.
Upcoming Construction
- Phase 1 (Pactola Dam to the Pennington-Lawrence County Line) permanent surfacing takes place this summer and will be completed by the end of July 2025. Currently, there are approximately two miles of gravel and three miles of hard surface between Pactola Dam and the Pennington-Lawrence County Line.
- During this time period, roadway users can expect the use of flaggers and pilot cars with delays up to 15 minutes.
- Closure C (Sheridan Lake Road to Be Still Road) takes effect on Monday, April 28, 2025, and ends Friday, June 13, 2025.
- During this time period, the closed roadway will not be open to through traffic. Outside of the closure, but within the construction area, travelers can expect pilot cars and wait times, the use of large construction equipment, narrowed driving lanes, and loose gravel surfacing.

Click on image to enlarge.


Current Construction Updates
- Phase 1 construction is complete until spring 2025, when crews will place final surfacing. Currently, there are approximately two miles of gravel and three miles of hard surface between Pactola Dam and the Pennington-Lawrence County Line.
- Phase 2 construction operations currently involve off-road grading, tree clearing, and logging operations. The contractor is using a pilot car and flaggers as needed from 7 a.m. to 6 p.m. M.T. on weekdays and some Saturdays.
Upcoming Construction Updates
- Phase 1 (Pactola Dam to the Pennington-Lawrence County Line) permanent surfacing takes place this summer and will be completed by the end of July 2025. Currently, there are approximately two miles of gravel and three miles of hard surface between Pactola Dam and the Pennington-Lawrence County Line. During this time period, roadway users can expect the use of flaggers and pilot cars with delays up to 15 minutes.
- Phase 2 construction is underway and the first closure begins this spring. Closure C (Sheridan Lake Road to Be Still Road) takes effect on Monday, April 28, 2025, and ends Friday, June 13, 2025. During this time period, the closed roadway will not be open to through traffic. Outside of the closure, but within the construction area, travelers can expect pilot cars and wait times, the use of large construction equipment, narrowed driving lanes, and loose gravel surfacing.
- Closure D (Be Still Road to Calumet Road) begins on Tuesday, Aug. 12, 2025, and ends on Friday, Oct. 17, 2025. Closure E (Pactola Dam to Taylor Ranch Road) begins on Monday, Oct. 20, 2025, and ends on Friday, March 6, 2026.
- The posted detour for these closures is S.D. Highway 44 and U.S. Highway 16.

Click on image to enlarge.


Construction Updates
- Phase 2 construction operations currently involve off-road grading, tree clearing, and logging operations. The contractor is using a pilot car and flaggers as needed from 7 a.m. to 6 p.m. (MT) on weekdays and some Saturdays.


Construction Updates
- Phase 1 construction is complete until spring 2025, when crews will place final surfacing. Currently, there are approximately two miles of gravel and three miles of hard surface between S.D. Highway 44 and the Pennington-Lawrence County Line.
- Phase 2 construction operations currently involve off-road grading, tree clearing, and logging operations. The contractor is using a pilot car and flaggers as needed from 7 a.m. to 6 p.m. MT on weekdays and some Saturdays.
January Drone Flyover

